Long Harbour Plant

Long Harbour Processing Plant

Vale Newfoundland & Labrador Limited

|

Canada

|

2014–2015

50,000 tpa nickel rounds.

5,000 tpa copper cathodes.

2,500 tpa cobalt rounds.

Challenges

  • Vale Newfoundland & Labrador Limited aimed to finish engineering and construction work on the processing plant in a timely manner to eliminate any impact of project schedule.
  • Any unfinished and problematic scope needed to be identified to reduce field engineering changes and rework.
  • The project also involved organizing and incorporating approximately one terabyte of existing data or deliverables into the phase 2 plan, including 43,800 engineering and vendor deliverables from over 350 vendor packages from an earlier project phase.

Solutions

  • Collected site data through complete and detailed area walk-downs to assess the installation condition and status of each plant area.
  • Compiled and communicated collected site data using iPads and mobile data applications for “instant-office” connections with low dependency on IT infrastructure.
  • Used queryable 3D iModels in the field to determine unfinished or problematic scope, resulting in reduced field-engineering changes and rework.
  • The engineering and integrated-project teams collaborated to reduce deliverable milestones by two months, meeting an aggressive project recovery schedule, and reducing cost.

Highlights

  • Met all major engineering milestones and the engineering project ran significantly under original budget.
  • Completed installation of the 2015 contract packages on schedule, with the remaining scope scheduled for completion in 2016.
  • Process design modifications made during project execution permitted a phased approach to construction and subsequent interim operations.
  • The engineering team modified design deliverables in a timely manner to eliminate any impact on the project schedule.

What's your challenge?


Let's connect.

Related projects