
Long Harbour Processing Plant
Vale Newfoundland & Labrador Limited
|
Canada
|
2014–2015
50,000 tpa nickel rounds.
5,000 tpa copper cathodes.
2,500 tpa cobalt rounds.
Challenges
- Vale Newfoundland & Labrador Limited aimed to finish engineering and construction work on the processing plant in a timely manner to eliminate any impact of project schedule.
- Any unfinished and problematic scope needed to be identified to reduce field engineering changes and rework.
- The project also involved organizing and incorporating approximately one terabyte of existing data or deliverables into the phase 2 plan, including 43,800 engineering and vendor deliverables from over 350 vendor packages from an earlier project phase.
Solutions
- Collected site data through complete and detailed area walk-downs to assess the installation condition and status of each plant area.
- Compiled and communicated collected site data using iPads and mobile data applications for “instant-office” connections with low dependency on IT infrastructure.
- Used queryable 3D iModels in the field to determine unfinished or problematic scope, resulting in reduced field-engineering changes and rework.
- The engineering and integrated-project teams collaborated to reduce deliverable milestones by two months, meeting an aggressive project recovery schedule, and reducing cost.
Highlights
- Met all major engineering milestones and the engineering project ran significantly under original budget.
- Completed installation of the 2015 contract packages on schedule, with the remaining scope scheduled for completion in 2016.
- Process design modifications made during project execution permitted a phased approach to construction and subsequent interim operations.
- The engineering team modified design deliverables in a timely manner to eliminate any impact on the project schedule.
Project numbers
43,800 engineering deliverables350 vendor packages