Silicon Valley Rapid Transit Project/BART

Alternative transit connecting San José to the San Francisco Bay area

Santa Clara Valley Transportation Authority | United States | 2008-2017

16.3 mile extension

Tunneling in a dense urban environment

USD 6 billion in project costs

Challenges

  • It was necessary to extend the BART system into downtown San José to provide a transit alternative to the highly congested I-680 and I-880 commuter corridors.
  • San José was then able to become connected with the rest of the San Francisco Bay area.
  • The extension meant that tunneling was needed through a dense urban environment in soft fluvial soils.

Solutions

  • Hatch (in JV) was responsible for designing the tunnel segment: the alignment, tunnel lining and cross passage (CP) design, settlement analysis and mitigation, coordination with BART facilities standards, station interfaces, cost estimating, construction sequencing, and specification of owner-procured tunnel boring machine (TBM) and lining systems.
  • We also were responsible for project management support services, project cost control, maintaining a trend log and estimating changes, performing independent cost estimates of proposed changes, and schedule controls for the entire Silicon Valley Rapid Transit project.
  • Extensive geotechnical investigations included 101 borings, 179 cone-penetrometer tests, and six pumping tests.

Highlights

  • The BART extension will provide alternate transit options.
  • It will reduce traffic congestion and eliminate approximately 16,000 tons of greenhouse gases in a year.
  • It will also provide support for development along the length of the corridor.
  • Overall cost and schedule-control management were seamlessly provided for a highly complex transit project.

How we can help you

If you have a problem that needs to be solved, please get in touch.

Contact Us