Muga Potash Plant

Wet processing plant—basic and detailed engineering

Geoalcali Sociedad Limitada (S.L.) (owned by Highfield Resources Limited) | Spain | 2015-2017

Michael X. Schlumpberger |

Project numbers

Around 500,000 t/y of granular potash in first phase
80,000 hours of detailed engineering
20 months from basic through detailed engineering
Total project CAPEX estimated at €267 million (≈USD$315 million)

Services and technologies provided

Potash
Engineering
Project Management