Kolomela mine Sishen South

Sishen South project

Kumba Iron Ore (Anglo American)

|

South Africa

|

2008–2011

18 million labor-hours with 0 LTIs.

Below budget with no contingency used.

Completed project ahead of schedule.

0.7 Mtpa over design capacity in first year of production.

Challenges

  • Anglo American aimed to establish a nearby greenfield processing-and-material-handling facility to produce an initial 9 Mtpa of iron ore from the Kolomela mine.
  • The project involved developing the Kolomela mine as a direct-shipping operation to meet the increased demand for high-grade iron ore.

Solutions

  • Provided full engineering, procurement, project, and construction management for the plant, stockyard, and load-out facility.
  • Expanded the purpose of the Kolomela mine to include a direct-shipping operation.
  • Designed and managed the rail link from the mine to the main Sishen–Saldanha line as a separate project.
  • Assumed construction management of the housing development for operations staff in 2011 and completed 718 houses.

Highlights

  • Winner, Kumba Iron Ore’s Gold “Laurel” Safety Award (2011).
  • Project completed within budget and ahead of schedule.

Project numbers

R6.5 billion (Hatch’s role: R2.3 billion)
30,000 m3 of concrete poured
1,450 tonnes of plate work
1,300 tonnes of structural steel
1,100 tonnes of conveyors
335 mechanical equipment items
205 km of electric and instrument cables
26 km of piping
840 jobs created