Hatch Meadowbank Gold Project

Meadowbank Gold project

Agnico-Eagle Mines Ltd.

|

Canada

|

2007–2010

8,500 tpd capacity gold concentrator.

28-MW diesel-power generation plant with heat recovery.

US$272 million CAPEX (Hatch's scope).

−50ºC Arctic winter conditions.

Challenges

  • Agnico-Eagle Mines Ltd.'s project involved the design of facilities for Arctic conditions: ultra-low temperatures, drifting snow in wintertime and wet ground, and permafrost conditions in summer.
  • It also included managing the logistics of a remote air-and-barge-access location and a 10-week shipping season in mid-to-late summer.
  • All power and heat would be supplied from an on-site, diesel-power generation plant.
  • The facility needed to operate in a remote, greenfield location with no existing support infrastructure of any kind.

Solutions

  • Provided detailed engineering, procurement, and construction support services for the 8,500 tpd gold processing facilities and site infrastructure, including power-generation plant.
  • Used waste material from pre-stripping as bulk construction material for erecting dikes and for fill materials around the site.
  • Erected eight major buildings during summer so concrete and equipment installation could continue indoors during the harsh Arctic winter conditions.
  • Designed the power plant to include a heat-recovery system, providing heat to the entire mine site complex.

Highlights

  • Mobilized more than 50,000 tonnes of material and equipment to the site over a purpose-built, 115-km, all-weather road from Baker Lake.
  • Procured equipment and construction materials in time to be all shipped on barges during a short 10-week ice-free period in summertime.
  • Our procurement and logistics strategy helped meet the construction schedule and improved working conditions for contractors through the winter.
  • Designed diesel-fired power plant, heat-recovery, and heat-distribution systems that were rigorous enough for Arctic conditions and resulted in cost savings and schedule improvements.

Project numbers

US$272 million capital cost (Hatch's scope)
8,500 tpd gold concentrator
28 MW diesel-power generating plant
115 km purpose-built, all-weather road
40,000,000 L diesel-storage facility at Baker Lake
5,600,000 L diesel-storage & dispensing facility at the site
10 bay truck shop and office complex
350-person camp accommodations
50,000 tonnes of material and equipment shipped in 10 weeks