Tenke Fungurume Mine

Tenke Fungurume Mine

Freeport-McMoRan Copper & Gold Inc.

|

Democratic Republic of Congo

|

2011–2012

125,000 to 190,000 tpa increase in copper production.

10,000 to 20,000 tpa increase in cobalt production.

Remote location with limited transport access.

Brownfield project.

Challenges

  • In order to maximize the project's return on investment, the client established an extremely short project schedule.
  • The project involved construction within an operating plant.
  • The location presented challenges regarding the importation of equipment, materials, and skilled labor.

Solutions

  • Completed detailed engineering and procured equipment. Also provided construction-support services, such as field engineering and cost/progress reporting.
  • Employed and constructed major new process equipment and facilities, including new high-grade pregnant leach-solution clarifier; four new solvent-extraction mixer-settlers; new electrowinning tankhouse; and an upgraded reagent processing and distribution system.

Highlights

  • Worked with Freeport-McMoRan as an integrated team.

Project numbers

125,000 to 190,000 tpa increase in copper production
10,000 to 20,000 tpa increase in cobalt production