green batteries

Forge Battery Cell Production Facility

Advanced lithium-ion cell production with Atomic Armor™ Technology

Forge Battery

|

Morrisville North Carolina, U.S.A

|

2023-2024

USD$100 million grant from the US Department of Energy (DOE)

300 Wh/kg energy density due to Forge Nano’s Atomic Armor coating

2 GWh annual battery cell manufacturing facility

Challenges

  • The primary challenge was rapidly scaling from R&D operations to a fully integrated, high-volume commercial battery manufacturing facility.

  • Detailed battery cell assembly drawings were still in development at project start, requiring early-stage definition to support scalable manufacturing design.

  • Budget discipline was critical as Forge Battery advanced the project while actively securing private capital and federal funding.

  • The selected facility was insufficient, and an additional structure needed to be designed with limited footprint for expansion.

Solutions

  • Hatch leveraged its proven process-engineering toolset to define scalable production requirements, significantly reducing implementation risk during Forge Battery’s transition to mass manufacturing.

  • Hatch’s battery cell design and process experts served as subject matter experts advancing product-level assembly definitions using deep experience in R&D-to-commercialization transition.

  • Hatch worked closely with Forge Battery leadership to refine scope around critical priorities, maximizing deliverable value while supporting private investment and federal funding objectives within budget.

  • Hatch coordinated with the facility contractor to develop concepts that fit within available footprint and provided the necessary process space for battery cell production.

Highlights

  • Enabled the successful transition of Forge Battery from R&D planning to gigafactory-scale production through a fully integrated design FEED package.

  • Delivered end-to-end production process and balance-of-plant integration to support a 2 GWh annual battery cell manufacturing facility.

  • Advanced product-level cell assembly definitions using deep commercialization expertise to de-risk large-scale implementation.

  • Hatch’s work directly supported Forge Battery’s successful pursuit of $100 million US Department of Energy (DOE) funding award.

“Hatch’s disciplined FEL 2/3 process, beginning with process engineering and extending through facility requirements development and battery manufacturing equipment selection, provided exactly the clarity our cylindrical battery start-up required. Their disciplined approach and dependable guidance were invaluable during a complex and rapidly evolving effort.”

Bill Brueggen | Project Manager, Battery Manufacturing Equipment, Forge Battery

Project Numbers

  • USD$100 million grant from the US Department of Energy (DOE)
  • 300 Wh/kg energy density due to Forge Nano’s Atomic Armor coating
  • 2 GWh annual battery cell manufacturing facility