Oxec II Hydroelectric Project

Oxec II Hydroelectric Project

Powering Guatemala with green energy

Solel Boneh Guatemala

|

Guatemala

|

2014 - 2018

56 MW greenfield hydropower project in Guatemala.
First cellular cofferdam in Guatemala.
40% savings in spillway concrete volume.
4-month reduction in overall construction schedule.

Challenges

  • A high-magnitude flood design complicated the spillway energy-dissipation design.
  • A high-magnitude, temporary diversion flood complicated the diversion works.
  • Unstable ground and a poor-quality foundation have been associated with landslides during excavation.
  • A large volume of work had to be accomplished within a limited, compressed schedule.

Solutions

  • Changed the spillway stilling-basin design to an optimized submerged roller bucket design, resulting in up to 40% savings in the concrete volume of the spillway.
  • Reduced the length of the cofferdam and temporary works with the revised spillway design. 
  • Replaced the original conventional cofferdam with a cellular alternative, resulting in a much smaller footprint and smaller excavation.

Highlights

  • The cofferdam eliminated a major phase in diversion, reducing the overall construction schedule by 4 months and achieving a remarkable reduction in bank excavation.
  • The first of its kind built in Guatemala, the cofferdam has 29 cells, is nearly 300 metres long, and consists of 2,000 tons of steel and over 50,000 mof fill.
  • The cofferdam resists fast flows, controls the release of sediment, and exhibited high reliability and safety during its installation and life in service, needing no remedial works after flood events.
  • The fill material was processed with a view to removal methodology. The maximum size of the aggregate was limited so the cell fill can be mixed with water and pumped off the project site.

Project Numbers

56-MW greenfield hydropower project in Guatemala
200-m-long concrete gravity dam
41 m
high powerhouse
150,000 m3 of concrete construction in less than 30 months
4 spillway radial gates (12 m W x 16.5 m H) to pass an extreme flood of 6144 m3/s
29-cell cofferdam designed for a diversion flood of 2,810 m3/s
50,000 m3 of fill for Stage 1 cofferdam
1,800 sheet piles constructed in a 4-month period

What's your challenge?


Let's connect.

Related Projects