Exploits River Hydroelectric Assets Condition Assessment
Upgrading aging hydro plants with a levelized CAPEX plan
Nalcor Energy | Canada | 2012
100-year-old
hydro plants assessed
HydroVantageTM
and eInspector tools added value
20-year
levelized CAPEX plan for upgrades produced
Challenges
- Nalcor Energy needed a technical assessment, CAPEX plan, and an asset management plan in order to bring three aging hydroelectric facilities up to the standards expected of today's utilities.
- The 100-plus-year-old plants were obtained from Abitibi Bowater Paper Company in 2009.
- The Grand Falls, Bishop’s Falls, and Buchans generating stations located in the Canadian province of Newfoundland and Labrador, have a combined output of 101 MW from 15 units, with associated water-retaining structures needed to supply the operation.
Solutions
- The HydroVantage software system was used to establish the optimal, risk-informed intervention strategy for the next 20 years.
- A physical inspection was undertaken of all facilities and past O&M records were evaluated, along with a detailed condition assessment of all assets in the system.
- Alternatives such as overhaul, refurbishment, upgrade, or replacement were considered, and their costs were estimated.
- A risk-based assessment of alternatives led to a recommended capital expenditures plan, which was also levelized to satisfy financial constraints.
Highlights
- The proprietary eInspector tool was customized to collect and store the data on physical assets.
- HydroVantage prioritized CAPEX, based on minimizing risk due to equipment failures.
- The owner’s annual CAPEX constraints were levelized for the 20-year CAPEX plan.
Project numbers
101 MW from 15 units20-year CAPEX plan
Services & technologies provided
What's your challenge?
Related projects
![Quebrada-Leon-Flood-Control-Works_thumb](/-/media/Quebrada-Leon-Flood-Control-Works_thumb.jpg?h=175&iar=0&w=265&hash=2BCE29C6430EA482245D20B44964DB48)
Quebrada Leon Flood Control Works
Trujillo, Peru
![XE-100 4 Pack Plant](/-/media/Hatch-Corporate/Projects/XE-100-4-Pack-Plant-_thumbnail.jpg?h=175&iar=0&w=265&hash=5114CC0BCC2D13F024B8A3E9397D6521)
Xe-100 reactor development program
United States
![Kemano Second Tunnel (T2) Project](/-/media/Hatch-Corporate/Projects/MetalsMinerals/TBM_cutterhead-thumb.jpg?h=175&iar=0&w=265&hash=A5F3C959786836E954BB0F61D5AB6EEE)
Kemano Second Tunnel (T2) Project
British Columbia, Canada
![GrandFallsDam Thumbnail](/-/media/Hatch-Corporate/Projects/Energy/GrandFallsDam.jpg?h=175&iar=0&w=265&hash=0113A689EF1AD759CE2D6032F296F53D)
Grand Falls Dam and Spillway Rehabilitation
Grand Falls, Newfoundland, Canada
![Mesquite Solar 1 project by Hatch](/-/media/Hatch-Corporate/Projects/Energy/Mesquite-Solar_265x175.jpg?h=175&iar=0&w=265&hash=8886AF5A49BB513D07EBA52C9AB31A34)
Mesquite Solar 1
United States of America
![Kelso Dam Thumbnail](/-/media/Hatch-Corporate/Projects/Energy/2021/KelsoDamThumbnail.jpg?h=175&iar=0&w=265&hash=A4A8C91DFA6AEF28FF8864EA14DED22C)
Kelso Dam: urgent repairs and rehabilitation project
Milton, Ontario, Canada
![Oxec II Hydroelectric Project thumbnail](/-/media/Hatch-Corporate/Projects/Energy/OxecII1Thumb.jpg?h=175&iar=0&w=265&hash=A98D128D3373A856BF366B51A30DC87F)
Oxec II Hydroelectric Project
Guatemala
![Rainy River](/-/media/Hatch-Corporate/Projects/Energy/Rainy-Riverthumb.jpg?h=175&iar=0&w=265&hash=75DD4957634154F3E2A2BD4AF5246BC1)
Rainy River Solar
Canada
![Thunder Bay Hydro Solar Rooftop](/-/media/Hatch-Corporate/Projects/Energy/Thunder_Bay_Hydro_Victoriaville_Parkade_Aerial_265_175.jpg?h=175&iar=0&w=265&hash=1E7518BE18FCCD4F92547208AD50545D)
Thunder Bay solar projects
Canada
![Niagara Tunnel](/-/media/Hatch-Corporate/Projects/Infrastructure/NiagaraTunnelthumb.jpg?h=175&iar=0&w=265&hash=E7AF6A4F459209389964B940B87E9C51)
Niagara Tunnel
Canada